Chicos clockworks uses job order costing for its custom


Question - Chico's Clockworks uses job order costing for its custom clock-making business. Job GF1260 is a custom-made grandfather clock. Chico's job cost sheet for Job GF1260 shows a total cost of $4,265, including direct labor of 50 hours at $20 per hour. Overhead is applied at 100% of direct labor cost. What is the direct materials cost for Job GF1260?

A: $1,000

B: $3,455

C: $2,265

D: $2,895