Cheyenne Co. purchased land as a factory site for $504,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months.

The company paid $52,920 to raze the old buildings and sold salvaged lumber and brick for $7,938. Legal fees of $2,331 were paid for title investigation and drawing the purchase contract. Cheyenne paid $2,772 to an engineering firm for a land survey, and $85,680 for drawing the factory plans. The land survey had to be made before definitive plans could be drawn. Title insurance on the property cost $1,890, and a liability insurance premium paid during construction was $1,134. The contractor’s charge for construction was $3,452,400. The company paid the contractor in two installments: $1,512,000 at the end of 3 months and $1,940,400 upon completion. Interest costs of $214,200 were incurred to finance the construction.

Determine the cost of the land and the cost of the building as they should be recorded on the books of Cheyenne Co. Assume that the land survey was for the building.

Request for Solution File

Ask an Expert for Answer!!
Financial Accounting: Cheyenne co purchased land as a factory site for 504000 the
Reference No:- TGS01698432

Expected delivery within 24 Hours