Case-suing for breach of contract


Case Problem:

In May, Watts was awarded a construction contract, based on its low bid, by the Cullman County Commission. The contract provided that it would not become effective until approved by the state director of the Farmers Home Administration (now part of the U.S. Department of Agriculture Rural Development Office). In September, construction still had not been authorized and Watts wrote to the County Commission requesting a 5 percent price increase to reflect seasonal and inflationary price increases. The County Commission countered with an offer of 3.5 percent. Watts then wrote the commission, insisting on a 5 percent increase and stating that if this was not agreeable, it was withdrawing its original bid. The commission obtained another company to perform the project, and on October 14, informed Watts that it had accepted the withdrawal of the bid. Watts sued for breach of contract. Explain whether Watts will prevail and why or why not.

Your answer must be, typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.

Request for Solution File

Ask an Expert for Answer!!
Business Law and Ethics: Case-suing for breach of contract
Reference No:- TGS01972095

Expected delivery within 24 Hours