Can a contractor claim that liquidated damages should be


Can a contractor claim that liquidated damages should be limited? Because of political unrest, only 20% of rooms are occupied. Liquidated damages are set to $30000 per day -> reasonable amount Contractor is late 15 days. Contractor claims that 20%*30000=$6000 per day should be paid, because only of rooms are occupied.