Calculating project simple-regular payback


Haig Aircraft is considering a project which has an up-front cost paid today at t = 0. The project will generate positive cash flows of $60,000 a year at the end of each of the next five years. The project's NPV is $75,000 and the company's WACC is 10 percent. What is the project's simple, regular payback?

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Calculating project simple-regular payback
Reference No:- TGS055444

Expected delivery within 24 Hours