Calculate the value of finished output


Question:

In a continuous flow process, the following information was collected in relation to production during the month of May:

 

Units

Work-in-progress at start of month (60% complete)

50,000

New units introduced for processing

80,000

Completed units transferred to store

100,000

Work-in-progress at end of month (20% complete)

30,000

Opening work-in-progress was valued at cost of £42,000. Costs incurred during the month were £140,000.

Required

Calculate the value of finished output and work-in-progress using the weighted average method.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Calculate the value of finished output
Reference No:- TGS02044471

Now Priced at $10 (50% Discount)

Recommended (99%)

Rated (4.3/5)