Discuss the below in detail:
Q: Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 30 units. The production run size is 40 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Then calculate the units that are available to promise. Customer orders are follows:
| WEEK |
Customer Order
|
| 1 |
32 |
| 2 |
15 |
| 3 |
6 |
| 4 |
0 |