Calculate the units-are available to promise


Discuss the below in detail:

Q: Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 30 units. The production run size is 40 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Then calculate the units that are available to promise. Customer orders are follows:

WEEK

Customer Order

1        32
2        15
3         6
4         0

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the units-are available to promise
Reference No:- TGS02052727

Expected delivery within 24 Hours