Calculate the total materials variance


Problem: Aco manufactures sleep pads/ Manufacturing standards per sleep pad based on 4,500 sleep pads per month:

Direct material of 5.25 at $5.00 per yard

Direct labor of 2 hours at $18.00 per hour

Overhead applied per sleep pad at $15,00

In April Aco actually produced 5,100 sleep pads using 27,250 yards of material at a cost of $5.25 per yard. Labor used was 11,250 hours at an average rate of $20.25 per hour. Actual overhead spending was $96,000.

Required: Calculate the total materials variance.

If you would like to score maximum but don't have adequate money to do precisely complete your academic tasks and thinking to skip the academic tasks, then stop and wait for a minute! At this point, it is prudent to take online assistance from the Total Materials Variance Assignment Help service, in order to excel your academic grades.

Tags: Total Materials Variance Assignment Help, Total Materials Variance Homework Help, Total Materials Variance Coursework, Total Materials Variance Solved Assignments

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the total materials variance
Reference No:- TGS03036271

Expected delivery within 24 Hours