Problem: The Tyson Company has provided the following information:

Direct
Month    Factory Labor Hours
Overhead

January     $92,095    4,600

February    103,056    5,280

March          83,802    3,760

April            89,594    4,320

May            108,694   5,720

June            87,404    3,880

a. Using the high-low method, calculate the total fixed factory overhead cost and the variable factory overhead cost per direct labor hour.

b. Prepare the cost function.

c. What would the total factory overhead cost be at a level of 5,000 hours?