Calculate the total cycle time necessary to manufacture


Chocolate Delights Company produces baking chocolate for use by commercial organizations. The company is analyzing its operations in preparation for reconfiguring its factory setup.

Currently, each batch of chocolate requires the following processes:

Function

Time (Minutes)

Receiving ingredients from vendors

90

Transporting ingredients to stockroom

100

Ingredient storage

6,400

Transporting ingredients to production area

75

Mixing ingredients

400

Cooking ingredients

180

Cooling chocolate

90

Packaging chocolate

160

Moving finished goods to warehouse

105

Storing finished goods in warehouse

20,500

Moving finished goods to trucks

150

a) Calculate the total cycle time necessary to manufacture a batch of chocolate.

b) Identify the value-added functions

c) Calculate the manufacturing cycle efficiency (MCE) of this process.

d) Assume that a management consultant has established a goal that Chocolate Delights Company increase its MCE to 5 percent or greater. Identify three possible areas in which the company could reduce its cycle time.