Calculate the total cost of ordering and carrying at the eoq


Dolphin Company predicts that it will use 25,000 units of material during the year. The expected daily usage is 200 units, and there is an expected lead time of five days and a safety stock of 500 units. The material is expected to cost $5 per unit. Dolphin anticipates that it will cost $50 to place each order. the annual carrying cost is $0.10 per unit.

1) Compute the order piont.
2) Determine the most economical order quantity by use of the formula.
3) Calculate the total cost of ordering and carrying at the EOQ point.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the total cost of ordering and carrying at the eoq
Reference No:- TGS0710134

Expected delivery within 24 Hours