Calculate the takt time for the information


Discuss the below:

Calculate the takt time for the following information:

1) 10 hour work day.

2) 2 Shifts

3) 45 minute lunch.

4) 45 minute set up at start of shift

5) 20 minute clean up at end of shift

6) 1296 units needing produced each day

7) Give your answers in seconds (2 decimal places)

8) How many parts will be made if the time to produce one full part is 14 seconds?