Calculate the spi and cpi for this project what will be


For a given 12-month project, the performance data at the review time was as follows:

PV= $10,000,

AC=$11,000,

EV= $11,000 and BAC= $50,000.

Based on those numbers:

1. Calculate the SPI and CPI for this project.

2. Based on the SPI value, is the project ahead of schedule or behind schedule?

3. Based on the CPI value, is the project under budget or over budget?

4. What will be value for the estimated cost at completion?