Calculate the scheduled completion time identify the


The following data were obtained from a project to design a new software package.

Activity Duration Predecessors

A 5 Days ---

B 8 Days ---

C 6 Days A

D 4 Days C, B

E 5 Days A

F 4 Days D, E, G

G 4 Days B, C

H 3 Day G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions.

a) Calculate the scheduled completion time.

b) Identify the critical path(s).

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G? 

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the scheduled completion time identify the
Reference No:- TGS01542386

Expected delivery within 24 Hours