Calculate the scheduled completion time


Problem: The following data were obtained from a project to build a pressure vessel:

Activity    Duration    Predecessors
A             4 weeks           ---
B             4 weeks           ---
C             3 weeks           B
D             2 weeks         A, C
E             3 weeks           B
F             5 weeks        D, E, G
G            2 weeks             B
H            6 weeks              F
I             3 weeks             G
J              1 week              I

Construct a network for the project. Then review and answer (A) and (B).

Q1. Calculate the scheduled completion time and identify the critical path.

Q2. What is the slack time (float) for activities A, D, E, and G?

Solution Preview :

Prepared by a verified Expert
Basic Statistics: Calculate the scheduled completion time
Reference No:- TGS01769147

Now Priced at $20 (50% Discount)

Recommended (95%)

Rated (4.7/5)