Calculate the prospective rate of return


A project has an initial cost of $140,000 and a calculated the salvage value after the16 years of $80,000. Estimated average annual disbursement is $16,000. Calculated the average annual receipts are $26,000. Assuming that annual receipts and the disbursement will be uniform, calculate the prospective rate of return before tax.