Calculate the projects etc activity a is 60 complete at a


From this data, calculate the project's ETC. Activity A is 60% complete at a cost so far of $100,000. It was estimated to cost $200,000 when finished.

It is at the end of week three of five. Activity B is 85% complete at a cost so far of $50,000. It was estimated to cost $80,000 when finished.

It is at the end of week four of five. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 dollars when finished.

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Calculate the projects etc activity a is 60 complete at a
Reference No:- TGS01062951

Expected delivery within 24 Hours