Calculate the progress of the project by completing the


Using EVA, Calculate the progress of the following project by completing the table below.

Activity

BCWS

BCWP

ACWP

Schedule Variance

Cost

Variance

SPI

CPI

A

2199

2199

2500

 

 

 

 

B

3933

3933

3500

 

 

 

 

C

3451

0

0

 

 

 

 

D

5219

5219

5500

 

 

 

 

E

5485

10285

9926

 

 

 

 

F

5191

3893

2200

 

 

 

 

1. Which activities are behind schedule?

2. Which activities are ahead of schedule?

3. Which activities have a cost overruns?

4. Which activities have a cost underrun?

Interpretation:

NOTE: Using EVA, calculate the progress of a project by completing a table and answering the questions. Write a short paragraph that interprets the data.