Calculate the probability that the project will be


A project completion time can be assumed to be represented by a normal distribution curve The project is expected to complete in 36 weeks with a path variance of 6.67 Base on the information provided, calculate: a. Calculate the probability that the project will be completed in 39 weeks or less b. The probability that the project will be completed in between 33.5 and 38 weeks c. With 95 percent probability, calculate the date the project can be completed.