Calculate the present value of each project at each of


Problem - Complete Problem that focuses on the evaluation of a capital budgeting project using methods of evaluation. In addition to answering letters A through C, use Excel to calculate the IRR for each project and discuss your results. This activity can be completed using appropriate office software;

NPV vs. Payback Method vs. Profitability Index

Alfred Stein is about to invest $1,000. Alfred is a very cautious man and would like to have some expert advice on which two projects is best for him. He has not told you his exact cost of capital because he likes to keep such information private, but he has told you to consider 8 percent, 10 percent, and 12 percent in your calculations. He has also told you that the salesperson from whom he expects to purchase his equipment has given him the following expected cost savings patterns:

Year Project 1 Project 2

1 $600 $300

2 $600 $600

3 $600 $800

4 $600 $700

Calculate the present value of each project at each of Alfred's potential costs of capital and indicate which project is acceptable at each.

Calculate the payback period for each project. Does your recommendation to Alfred change?

Calculate the profitability index for each project, using a cost of capital of 10 percent. Which project would you recommend Alfred pursue?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Calculate the present value of each project at each of
Reference No:- TGS02552114