Calculate the plantwide overhead rate for heurion


Heurion worked on five jobs in July. Data are as follows:

Job 741Job 742Job 743Job 744Job 745Balance, July 1$29,870$55,215$27,880$0$0Direct materials$25,500$39,800$14,450$13,600$8,420Direct labor cost$61,300$48,500$28,700$24,500$21,300Direct labor hours4,0003,4001,9801,6001,400

By July 31, Jobs 741 and 743 were completed and sold. The remaining jobs were in process.

Required:Be sure to read the instructions on each panel for additional guidance.

1. Calculate the plantwide overhead rate for Heurion Company. Round to the nearest cent.

2. Prepare job-order cost sheets for each job showing all costs through July 31. Round all amounts to the nearest dollar.

3. Calculate the balance in Work in Process on July 31.

4. Calculate Cost of Goods Sold for July.

Solution Preview :

Prepared by a verified Expert
Cost Accounting: Calculate the plantwide overhead rate for heurion
Reference No:- TGS02523989

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)