Problem: Given the following data, calculate the PAB. There are 50 units on band. (Week, Forecast Demand, Customer Orders, MPS Scheduled Receipts): (1, 75, 70, 100), (2, 50, 40, 0,), (3, 30, 40, 100), (4, 40, 50, 0), (5, 70, 50, 100), (6, 20, 5, 0). The demand time fence is at the end of week 3. The PAB of week four is: