Calculate the overhead controllable variance


In October, Harry Company reports 21,000 actual direct labor hours, and it incurs $115,000 of manufacturing overhead costs. Standard hours allowed for the work done is 20,000 hours. The predetermined overhead rate is $6 per direct labor hour. In addition, the flexible manufacturing overhead budget shows that budgeted costs are $4 variable per direct labor hour and $50,000 fixed. Compute the overhead controllable variance.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the overhead controllable variance
Reference No:- TGS055954

Expected delivery within 24 Hours