Calculate the overall risk factor for project


Assessment:

Quantitative Risk

Q: Assume the following information for an IT project.

Probability of failure  Consequences of failure
Maturity=.7                Cost=.9
Complexity=.7             Schedule=.7
Client Concerns=.5       Performance=.3
Programmer skill=.3      Future business=.5

Calculate the overall risk factor for this project. Would you assess this level of risk as low, moderate, or high? Why?