Calculate the operational availability for a power


Calculate the operational availability for a power generator with one scheduled maintenance per 1000 hours of operation and failure rate of 0.6 failures per 1000 hours. Preventive maintenance takes on average 8 hours, however, if the engine fails, it typically takes 26 hours to repair it. Logistics and administrative delays typically add extra 12 hours to the maintenance time.