Calculate the net present value for project a and project b


X-treme Vitamin Company is considering two investments, both of which cost $44,000. The cash flows are as follows:

Year Project A Project B
1 $ 46,000
$ 38,000
2
17,000

18,000
3
13,000

15,000

Use Appendix B for an approximate answer but calculate your final answer using the formula and financial calculator methods.

a-1. Calculate the payback period for Project A and Project B. (Round your answers to 2 decimal places.)

                           Payback Period

Project A year(s)

Project B year(s)

a-2. Which of the two projects should be chosen based on the payback method?

Project A

Project B

b-1.  Calculate the net present value for Project A and Project B. Assume a cost of capital of 8 percent. (Do not round intermediate calculations and round your final answers to 2 decimal places.)

Net Present Value

Project A $

Project B $

b-2.  Which of the two projects should be chosen based on the net present value method?

Project A

Project B

c. Should a firm normally have more confidence in the payback method or the net present value method?

Net present value method

Payback method

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Calculate the net present value for project a and project b
Reference No:- TGS02854209

Expected delivery within 24 Hours