Calculate the needed number of kanban cards station


Assignment:

Consider the below flow line

1182_Designing Kanban Control.jpg

The following table provides all the information need for designing Kanban control or Conwip control on this line. All times are in minutes

Machines (all data in minutes)

2185_Kanban designing machines.jpg

The daily demand is known to be 400 units per day. It is also known that the batch size for this line is 30 units per container. The line operates 24 hours each day without breaks.

a) Calculate the needed number of Kanban cards if each station will be controlled by Kanban. Use 10% safety factor.

b) If the entire line is to be controlled by Conwip system what should be the number of cards needed. For this, use 10% safety factor, and assume the card travel time from machine 6 to machine 1 is 12 minutes.

c) Which machine is the bottleneck machine on this line? Why?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the needed number of kanban cards station
Reference No:- TGS03010159

Expected delivery within 24 Hours