Calculate the minimum production cycle time in days


Assignment:

Notebook Company produces custom 3-ring binders with school logos for high schools in the Midwest. They mold binders in four standard colors and then imprint the school's logo on a to-order basis. The average daily demand for the base color notebooks is as follows: Green: 440 notebooks/day Blue: 220 notebooks/day Red: 290 notebooks/day Black: 370notebooks/day MySchool can produce 1, 580 notebooks per 24-hour day. It takes 8 hours to setup production for another color. Calculate the minimum production cycle time in days.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the minimum production cycle time in days
Reference No:- TGS03030087

Expected delivery within 24 Hours