Calculate the maximum output for a step


Assignment:

Q: Rockness Recycling refurbishes rundown business students. The process uses a moving belt, which carries each student through the five steps of the process in sequence. The five steps are as follows:

STEP DESCRIPTION TIME REQUIRED
PER STUDENT
1 Unpack and place on belt 0.6 minute
2 Strip off bad habits 0.8 minute
3 Scrub and clean mind 1.0 minutes
4 Insert modern methods 1.2 minutes
5 Polish and pack 0.4 minute

One faculty member is assigned to each of these steps. Faculty members work a 40-hour week and rotate jobs each week. Mr. Rockness has been working on a contract from General Eclectic, which requires delivery of 2,300 refurbished students per week. A representative of the human resources department has just called complaining that the company hasn't been receiving the agreed-upon number of students. A check of finished goods inventory by Mr. Rockness reveals that there is no stock left.

a. Calculate the maximum output for each step.

b. Which step is the bottleneck?