Calculate the materials efficiency and price variance


You are a student preparing for a job interview with a fortune 100 consumer products manufacturer. You are applying for a job in the finance department.

Calculate the materials efficiency and price variance, and the wage and labor efficiency variance for the month of May.Price Variance = (Actual Price of Input %u2013 Budgeted price of Input) x Actual Quantity of Input,Efficiency Variance= (Actual quantity of input used %u2013 Budgeted quantity of input allowed for actual output) x Budgeted price of input

You are a student preparing for a job interview with a Fortune 100 consumer products manufacturer. You are applying for a job in the Finance Department. This company is known for its rigorous case-based interview process. One of the students who successfully obtained a job with them upon graduation last year advised you to"know your variances cold!When you inquired further, she told you that she had been asked to pretend that she was investigating wage and materials variances. Per her advice, you have been studying the causes and consequences of variances. You are excited when you walk in and find that the first case deals with variance analysis. You are given the following data for May for a detergent bottling plant located in Mexico:

  • Actual
  • Bottles filled 340,000
  • Direct materials used in production 6,150,000 ozs
  • Actual direct material cost 2,275,000 pesos

Actual direct manufacturing labor-hours 26000 hours
Actual direct manufacturing labor-hours 784,420 pesos

  • Standards
  • Purchase price of direct materials 0.36 pesos / oz
  • Bottle size 15 oz
  • Wage rate 29.25 pesos / hour

Bottles per minute 0.50: Calculate the materials efficiency and price variance, and the wage and labor efficiency variances for the month of May.

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the materials efficiency and price variance
Reference No:- TGS0684305