Calculate the manufacturing cycle efficiency


The James Company collected the following information (in days) for November and December.

  • Novemeber/ December
  • Transporting product 2.0/3.0
  • Processing product 15.0/18.0
  • Inspecting product 1.0/1.2
  • Storing product 8.0/7.0

Required:
a. Calculate the manufacturing cycle efficiency for November and December.
b. Assume January's processing time will be the same as December's. If James' target for manufacturing cycle efficiency is 65%, what will January's target for non-processing times be?