Calculate the irr for each project


Problem 1: Consider the following two mutually exclusive projects:

Year    Cash Flow (X)    Cash Flow (Y)
0          -$ 19,300           -$19,300
1                8,675               9,750
2                8,750               7,625
3                8,625               8,525

Calculate the IRR for each project. (Round your answers to 2 decimal places. (e.g., 32.16)).

IRR
Project X 
Project Y

What is the crossover rate for these two projects? (Round your answer to 2 decimal places. (e.g., 32.16)).

Crossover rate    %

Problem 2: What is the NPV of Projects X and Y at discount rates of 0%, 15%, and 25%? (Negative amount should be indicated by a minus sign. Round your answers to 2 decimal places. (e.g., 32.16))

Discount rate    Project X    Project Y
0%      $ $
15%    $ $
25%    $ $

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Calculate the irr for each project
Reference No:- TGS01891842

Now Priced at $25 (50% Discount)

Recommended (90%)

Rated (4.3/5)