YearProject AProject B
0 -180,000 -18,000
1 50,000 10,000
2 100,000 15,000
3 150,000 12,000

Consider the following two mutually exclusive projects listed above:

Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?