Calculate the initial process capability and then


Design specifications require that a key dimension on a product measures 100 +/- 9 ounces. A process being considered for producing this product has a standard deviation of 3 ounces. Calculate the initial process capability and then recalculate when the process average shifts to 91. What can you say about the capability of the initial and the shifted process?