Calculate the future worth fw at 10 of a project that will


Calculate the future worth (FW) at 10% of a project that will save $25K per year for 20 years. The first cost is $120K, and the salvage value is $20K. Compare this with the PW and the EAW. (Answer: FW = $645K)