Calculate the forecasted cost at completion if total


1. Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.

a. FCAC = $7,000

b. FCAC =$17,000

c. FCAC =$13,000

d. FCAC = $37,000

2. The project cost estimate is allocated to

a. the various work packages in the project work breakdown structure

b. the resources in the project.

c. the committed costs in the project.

d. the stakeholders.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the forecasted cost at completion if total
Reference No:- TGS02560535

Expected delivery within 24 Hours