Calculate the expected time of each activity using msp


In the following table, project activities in days are listed with three time estimates for duration in days and prede- cessors for the activities.

Most Optimistic Likely Pessimistic

Activity Time Time Time Predecessors

a 5 7 12 —

b 8 8 8 —

c 2 6 10 a

d 12 14 19 a,b

e 6 6 12 c,d

f 3 12 18 b,e

g 6 8 10 f

a) Calculate the expected time of each activity using MSP.

b) Construct a Gantt chart using MSP.

c) Use MSP to draw a network diagram.

d) Assuming a 5-day workweek, calculate the critical path of the project.

e) Calculate the slack for the activities.