Calculate the expected time and variance of each activity


A project has the following data

activity

Immediate predecessor

Optimistic time

Most likely time

Pessimistic time

A

-

2

3

4

B

A

1

2

3

C

A

4

5

12

D

A

3

4

11

E

B

1

3

5

F

C

1

2

3

G

D

1

8

9

H

D,F

2

4

6

I

H

2

4

12

J

G

3

4

5

K

I,J

6

7

8

Required

Calculate the expected time and variance of each activity?

Draw a network diagram and identify critical path and project completion time?

What is the probability that the project will take more than 30 days to complete?

Request for Solution File

Ask an Expert for Answer!!
Project Management: Calculate the expected time and variance of each activity
Reference No:- TGS0914381

Expected delivery within 24 Hours