Calculate the expected bac using original estimate approach


Assignment: Project Management

Activity 1: An activity on the critical path of a project was scheduled to be completed within 12 weeks, with a budget of $8,000. During a performance review, which took place 7 weeks after the activity was initiated, it was found that 50% of the work had already been completed and that the actual cost was $4,500.

i. Calculate the EV of the activity.
ii. Calculate the CI and SI for the activity.
iii. Calculate the expected BAC using the original estimate approach.
iv. Calculate the expected BAC using the revised estimate approach.
v. Compare and discuss the results obtained in parts (iii) and (iv).

Activity 2: Identify a new product that is based on an innovation in technology, and draw up a strategic technical plan for its development. Be sure to discuss the risk factors at each stage, and indicate how you would deal with each.

Format your assignment according to the following formatting requirements:

i) The answer should be typed, using Times New Roman font (size 12), double spaced, with one-inch margins on all sides.

ii) The response also includes a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.

iii) Also include a reference page. The Citations and references must follow APA format. The reference page is not included in the required page length.

Solution Preview :

Prepared by a verified Expert
Project Management: Calculate the expected bac using original estimate approach
Reference No:- TGS03068673

Now Priced at $30 (50% Discount)

Recommended (91%)

Rated (4.3/5)