Calculate the es ef ls and lf times and the slack for each


ASSIGNMENT

Project Management

Directions: Sources must be cited in APA format. Refer to the "Assignment Format" page for specific format requirements.

Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project.

Can the project be completed in 40 weeks?

Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks.

Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?

71_Activity Diagram.jpg

Write in 4 pages double spaced APA with Times roman 12 font with reference.

The ebook is provided in the attached.

Format Requirements

Use the following format requirements on all submissions.
•Writing Style APA (American Psychological Association)
Note: To find detailed information on APA manuscript style guidelines on the Internet, go to www.apastyle.org.

•Margins 1" all sides
•Paragraphs The entire document should be double-spaced on standard-sized paper (8.5" x 11")
•Headings Bold
•Type Style and Size Times New Roman, 12 point
•Software MS Word

Attachment:- Successful-Project-Management-Chapter-5-Developing-the-schedule.pdf

Solution Preview :

Prepared by a verified Expert
Project Management: Calculate the es ef ls and lf times and the slack for each
Reference No:- TGS01568310

Now Priced at $10 (50% Discount)

Recommended (98%)

Rated (4.3/5)