Calculate the eoq determine the current ordering cost


A company manufacturing bicycles has a current annual demand of 1,500 bikes. In buying bike tires, they pay $14 per tire with an estimated carrying cost of 20% of the tire’s cost. Each order cost $25 to process. Orders are placed on the first of each month for an equal amount every month. Determine the current ordering cost, carrying cost and total inventory cost each year using the current order quantity. Calculate the EOQ. Determine the current ordering cost, carrying cost and total inventory cost each year using the quantity found from the EOQ calculation.