Calculate the delivery cycle time


Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:


Days
  Wait time 13.9     
  Inspection time 0.3     
  Process time 2.65     
  Move time 1.3     
  Queue time 3.7     

Required:
a.

Compute the throughput time. (Round your answer to 2 decimal places.)

  Throughput time days
b.

Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to 2 decimal places.)

   MCE   
c.

What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)

  Percentage of the production time %
d.

Compute the delivery cycle time. (Round your answer to 1 decimal place.)

  Delivery cycle time days