Calculate the critical ratio and the estimate at


Question 1

You have won a contract to supply 400 precast concrete units for a replacement bridge. You estimate the production cost for each unit to be $50,000. A planned production schedule has been agreed with the client and is given in the table below (14 months total).

During production you monitor the number of units produced and your actual costs, details are summarised in the table below. At the end of month 8 your CEO asks for a review

Project
Month

Planned

Actual

 

Output

Item Cost
($000)

Output

Item Cost

0

0

 

0

$0.00

 

20

$50.00

15

$55.00

2

20

$50.00

16

$50.00

3

20

$50.00

18

$50.00

4

25

$50.00

18

$58.00

5

25

$50.00

20

$50.00

6

25

$50.00

22

$55.00

7

25

$50.00

21

$52.00

8

30

$50.00

24

$57.00

9

30

$50.00

 

 

10

30

$50.00

 

 

11

35

$50.00

 

 

12

35

$50.00

 

 

13

40

$50.00

 

 

14

40

$50.00

 

 

a. Complete an earned value analysis using the information provided. Plot the BCWS, ACWP and BCWP on a graph at a suitable scale.

b. Calculate the Cost Performance Index (CPI) and Schedule Performance Index (SPI).

c. Calculate the Critical Ratio (CR) and the Estimate at Completion (EAC).

d. Interpret the results

Solution Preview :

Prepared by a verified Expert
Microeconomics: Calculate the critical ratio and the estimate at
Reference No:- TGS01145863

Now Priced at $30 (50% Discount)

Recommended (91%)

Rated (4.3/5)