Calculate the cost and schedule variances


Discussion:

Q: Given an activity in an advertising project whose planed cost was exist12,000 but actual cost to date is exist10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client by pleased or angry?