Calculate the completion time for the project


Use the given project information.

Activity Activity Time(weeks) Immediate Predecessor(s)

A 3 none
B 4 A
C 2 B
D 5 B
E 4 C
F 3 D
G 2 E,F

Calculate the completion time for the project. (Completion time = weeks)

Determine which activities are included on the critical path.

A, B, D, F, G
A, B, C, E, G