Calculate the best-case and worst-case npv


We are evaluating a project that costs $1,398,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 87,800 units per year. Price per unit is $34.65, variable cost per unit is $20.90, and fixed costs are $758,000 per year. The tax rate is 40 percent, and we require a return of 11 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent. Calculate the best-case and worst-case NPV figures.