Calculate the beginning of the production process


Morse Company manufactures basketballs. Materials are added at the beginning of the production process and conversion costs are incurred uniformly. Production and cost data for the month of July 2014 are as follows.


Production Data-Basketballs


Units

Percent
Complete
Work in process units, July 1


420
60 %
Units started into production


1,370


Work in process units, July 31


590
40 %
Cost Data-Basketballs




Work in process, July 1






    Materials
$740




    Conversion costs
550
$1,290


Direct materials


2,450


Direct labor


1,987


Manufacturing overhead


1,029


Calculate the following.
(1) The equivalent units of production for materials and conversion costs.



Materials
Conversion Costs
Equivalent Units

(2) The unit costs of production for materials and conversion costs. (Round unit costs to 3 decimal places, e.g. 2.257.)



Materials
Conversion Costs
Cost per unit
$
$

(3) The assignment of costs to units transferred out and in process at the end of the accounting period. (Round answers to 0 decimal places, e.g. 2,250.)

Costs accounted for:

   Transferred out
$
   Work in process, July 31

      Materials $
      Conversion costs
   Total costs
$

Prepare a production cost report for the month of July for the basketballs. (Round unit costs to 3 decimal places, e.g. 2.257 and all other answers to 0 decimal places, e.g. 2,250.)

MORSE COMPANY
Basketball Department
Production Cost Report
For the Month Ended July 31, 2014




Equivalent Units

Quantities
Physical
Units


Materials

Conversion
Costs


Units to be accounted for







   Work in process, July 1






   Started into production






      Total units















Units accounted for







   Transferred out




   Work in process, July 31




      Total units














Costs




Materials

Conversion
Costs


Total
Unit costs







   Costs in July


$
$
$
   Equivalent units





   Unit costs


$
$
$









Costs to be accounted for







   Work in process, July 1






$
   Started into production






      Total costs






$









Cost Reconciliation Schedule







Costs accounted for







   Transferred out






$
   Work in process, July 31







      Materials




$

      Conversion costs





   Total costs






$

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: Calculate the beginning of the production process
Reference No:- TGS0557112

Expected delivery within 24 Hours