Calculate the amount of slack time for each activity


Problem:

Consider a project having the following ten activities:

Activity

Immediate Predecessors

Normal Time (weeks)

A

none

7

B

none

3

C

A

5

D

A, B

6

E

C, D

4

F

D

4

G

C

9

H

E, G

8

I

E, F

6

J

H, I

5

Required:

Question 1) Draw a network diagram. Identify the activities on the critical path.

Question 2) What is the duration of the critical path?

Question 3) Calculate the amount of slack time for each activity.

Question 4) If activity I were delayed by 5 time units, what would be the impact on the project duration?

Solve the given numerical problem and illustrate step by step calculation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate the amount of slack time for each activity
Reference No:- TGS0880366

Expected delivery within 24 Hours