Calculate labor productivity


Assignment:

The manager of a crew that installs wood floors has tracked the crew's output over the past several weeks. Each worker works 35 hours per week, and cams $ 19 per hour. The wholesale cost of lumber to the company is $4 per square foot, and the company charges its customers $17 per square foot of flooring installed.

Week

Crew Size

Lumber used (sq. ft)

Flooring Installed (sq. ft)

1

5

480

420

2

4

351

325

3

2

220

200

a. Calculate labor productivity for each of the weeks shown.

b. Suppose that in addition to labor cost and wholesale lumber cost, the firm's overhead is 140% of its labor cost. Calculate multifactor productivity for each week.