Calculate expected duration and variance of critical path


Activity Immediate
Predecessor(s) Pessimistic Probable Optimistic
J -- 15 10 8
K -- 9 8 7
L J 10 6 5
M J 3 3 3
N K,M 9 5 1
O K,M 10 7 4
P L,N 10 8 3

a. Calculate the expected duration of each activity.
b. Calculate the expected duration and variance of the critical path.
c. Calculate the probability that the project will be completed in fewer than 30 time units.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Calculate expected duration and variance of critical path
Reference No:- TGS077135

Expected delivery within 24 Hours